Creating a Project


To create a project, click Top MenuProject

Blank Project

This creates a project with no tasks.

Copy Project

This clones the project and its entire task WBS. All project and task fields (including custom fields but excluding constraints), dependencies, resource assignments and file attachments are also copied. The new project is then replanned as per the new project's start date. If the original project had manually scheduled tasks, those tasks in the new project will have a similar duration and will start at the same time after the new project's start.

Use a Template

For more details, click here.

Import Microsoft Project

For more details, click here.